May 2022
Installation of B-Building roof panels (May 2022).
Overview of D-Building construction progress (May 2022).
Overview of B-Building construction progress (May 2022).
A-Building construction in-progress (May 2022).
Industrial water heating tanks installed (May 2022)
April 2022
Building B construction overview (Apr. 2022).
Installation of covered walkway columns and beams (Apr. 2022).
New lockers installed in Building H Locker Rooms (Apr. 2022)
Mar. 28, 2022
Click here for the latest on construction news and opening plans in a update letter to the school community. A virtual community meeting was held on Tuesday, Mar. 29, to discuss the official naming of the school.
March 2022
Building B windows being installed (Mar. 2022).
Building D kitchen drywall installations in-progress (Mar. 2022).
Building A construction continues (Mar. 2022).
Building C overview (Mar. 2022).
February 2022
Setting a curved roof beam for Building B (Feb. 2022).
Framing a partition wall between classrooms on the 2nd floor in Bldg C (Feb. 2022).
Overview of the Library / Dining Hall - Building D (Feb. 2022).
Overview of Building C (Feb. 2022).
January 2022
Finishing of a concrete beam in the future library and cafeteria (Bldg. D) in-progress (Jan. 2022).
Classroom Bldg. B construction in-progress (Jan. 2022).
Ductwork installation in classroom Bldg. C in-progress (Jan. 2022).
August 2021
Construction of the future library and cafeteria (Bldg. D) in-progress (Aug. 2021).
Work on classroom Bldg. C in-progress (Aug. 2021).
Future P.E. locker rooms (Bldg. H) construction in-progress (Aug. 2021).
July 2021
Bldg. B construction continues (July 2021).
Installing curb and gutter at driveway (July 2021).
Bldg. D columns and foundations in-progress (July 2021).
June 2021
Design of the roundabout at the Piilani Highway entrance to the school is nearing completion. Once permitting is complete construction will start, under Nordic PCL Construction Company's contract, with completion targeted for early next summer.
Bldg. B construction continues (June 2021).
Bldg. B construction in-progress (June 2021).
Setting Bldg. C decking for second floor, looking south (June 2021).
Rebar installation for Bldg. D column in cafeteria (June 2021).
Bldg. D columns and foundations in-progress (June 2021).
May 2021
Phase 2 construction continues and will build the administration building, two classroom buildings, the library and cafeteria, PE and locker room, basketball court and a temporary playfield. The opening is anticipated for School Year 2022-23. Phase 2 construction Notice To Proceed was issued on Oct. 12, 2020, following a delay caused by a bid protest.
Bldg. C construction in-progress (May 2021).
Installation of plumbing at Bldg. D restrooms (May 2021).
Setting CMU blocks at Bldg. C (May 2021).
Installation of irrigation water tank (May 2021).
April 2021
Phase 2 construction in-progress.
Construction on Classroom Bldg. C interior walls in-progress (Apr. 2021).
Classroom Bldg. B exterior walls and foundations under construction (Apr. 2021).
Construction in-progress on the Cafeteria & Library Bldg. (Apr. 2021).
January 2021
Community Meeting Materials (Jan. 12, 2021)
|
|
Phase 2 constuction begins work on key buildings and areas marked in yellow.
Phase 1 mass grading and site preparation cleared the way for Phase 2 construction to begin.
Phase 2 construction begins on new buildings and key facilities.